Single County Project

2022. 06. 11 72
Share:

Project introduction: Shandong Heze Shanxian Waste Incineration Power Plant is located 1.5 kilometers northeast of Shanxian County. It was constructed by Shenzhen Energy Environmental Protection Co., Ltd., covering an area of 67,263 square meters. It is equipped with 2×400T/D waste incinerators + 1×15MW condensing steam type The steam turbine generator set can process 292,000 tons of garbage annually, generate 101 million kWh of electricity annually, and save 26,400 tons of standard coal. Acid, activated carbon jet adsorption and bag filter treatment can reach EU 2000 standard


Project progress: Boiler professional is making preparations for baking furnace


The overall commissioning and operation of the professional closed cooling water system and drainage system of the steam turbine has been completed, and the circulating water pipeline has been flushed.


  All parameters of the DCS disk are searched and checked. After the deoxidation water supply system and the condensate water system are tested, the circulating water system is tested after the replacement of the circulating water and the connection of the condenser pipes are completed. The external oil line is now being flushed and filtered


  • Prev
  • Next
  • Service
  • Message
  • Online Service